Certified quality
Factory production control, welding quality and management systems are certified by independent bodies.
Inspection marking (VT/PT) on welded details
Our statement on execution
Fabrication in accordance with EN 1090-2, Execution Class EXC3, under certified Factory Production Control according to EN 1090-1 and welding quality requirements according to EN ISO 3834-2.
Scope and certificate numbers
Certificates in detail
Six certificates: factory production control, welding quality, three management systems — and one product certificate, for the column types SR 10 and SR 13.
Company certificatesEN 1090-1
Factory production control
Certified factory production control for structural steel components. EN 1090-2 — Execution Class EXC3.
Copy on request
Company certificatesEN ISO 3834-2
Welding quality requirements
Comprehensive quality requirements for fusion welding.
Copy on request
Product certificationEN 40-5
Lighting columns SR 10 · SR 13
Certificate of constancy of performance (system 1) for the octagonal steel lighting columns SR 10 and SR 13.
Copy on request
Management systemsISO 9001
Quality management
Engineering, design, manufacture and execution of steel structures, equipment and lighting poles.
Copy on request
Management systemsISO 14001
Environmental management
Engineering, design, manufacture and execution of steel structures, equipment and lighting poles.
Copy on request
Management systemsISO 45001
Occupational health & safety
Engineering, design, manufacture and execution of steel structures, equipment and lighting poles.
Copy on request
EN 40 type tests
10 m and 13 m octagonal columns tested to EN 40-2, EN 40-3-1, -3-2, -3-3 and EN 40-5. · GIM-TEST, Banja Luka
Certificates are subject to periodic surveillance and renewal. Copies of the current certificates are available on request.
Certification
What applies to your order
Certified factory production control for our steel fabrication, a product certificate for two column types, and project-specific engineering and documentation for every other configuration.
Manufacture of steel construction parts, components, kits and structures in our plant
EN 1090-2 — Execution Class EXC3. Factory production control certified to EN 1090-1 (certificate 1017-CPR-13.701.692) · welding quality requirements to EN ISO 3834-2.
Lighting column types SR 10 and SR 13
Certificate of constancy of performance 1017-CPR-15.585.895 (system 1), type-tested to EN 40.
Other configurations — standard-range poles for a given site, high masts, special poles, custom fabrication and the monopole development programme
Project-specific engineering and documentation: structural verification to EN 40-3 or the Eurocodes as the project requires, shop drawings for approval and the inspection documents agreed in the order.
Fabrication statement
Fabrication in accordance with EN 1090-2, Execution Class EXC3, under certified Factory Production Control according to EN 1090-1 and welding quality requirements according to EN ISO 3834-2.
Reference standards
Applied per order — not certificates
We name a standard as a certificate only where an independent body has certified us. The following standards are the basis of design and execution, applied as the order requires.
- EN 40-3
- Lighting columns — design and verification
- EN 1991-1-4
- Wind actions, with national annex
- EN 1993-3-1
- Towers and masts
- EN 50341-1
- Overhead electrical lines — by the line designer
- EN 1090-2
- Execution of steel structures
- EN ISO 1461
- Hot-dip galvanizing
- EN 10025-2
- Structural steels
- EN 10204
- Inspection documents (3.1)
- EN ISO 10684
- Galvanized fasteners
Quality control
Quality built into every step
- Testing
- Visual and non-destructive testing by personnel qualified to EN ISO 9712
- Materials
- Plates and sections with inspection certificates 3.1 to EN 10204 · identification and traceability as required by the execution class
- Dimensions
- Length, straightness, cross-section and base plate checked before release
- Welding
- Welding coordination by IWE-qualified welding engineers · welders qualified to EN ISO 9606-1



Inspection points along the production route
- 01Material receipt3.1 certificates
- 02Cuttingblank check
- 03Formingprofile check
- 04Weldingto qualified WPS
- 05VT / NDTdimensional check
- 06Galvanizingpartner plant
- 07Final inspectioncoating & marking
- 08Dispatchdocuments
Engineering
From enquiry to shop drawing
Every project-engineered pole, mast or monopole follows the same route — design inputs, structural design, shop drawings and a weld and inspection plan — before fabrication is released.
- 01
Design inputs
Site, loads, equipment and standards agreed with the client.
- 02
Structural design
Client’s design, or project design by licensed structural engineers.
- 03
Shop drawings
Drawings, developed blanks and CNC nesting.
- 04
Weld & inspection plan
WPS, inspection points and documents per order.
- 05
Fabrication
Released after design approval.
Design responsibility
Agreed for each project: we manufacture to the client’s approved design, or supply a project-specific structural design prepared by licensed structural engineers. Shop drawings are released for fabrication after design approval.
Tools & data
- Analysis
- Dlubal RFEM · SAP2000
- CAD
- AutoCAD · Autodesk Inventor
- CAM
- Developed blanks and nesting for CNC cutting
- Exchange
- DWG / DXF · STEP · IFC
Documents
With the delivery — as agreed in the order
- Material certificates 3.1 to EN 10204
- Inspection records and dimensional checks
- Galvanizing certificate
- Declaration of Performance where CE marking applies
- Drawings and delivery list, marked to the sections
Enquiry
Request a technical manufacturing review
Send drawings, loads and specifications — we review manufacturability before we quote.