One plant — the full fabrication chain
Cutting, forming, welding, inspection and loading take place in our own halls in Kočani. Long sections move between the work stations on our own overhead cranes and leave the plant fully documented.
Main hall — tandem press brake, CNC cutting and overhead cranes
Plant at a glance
From the plate to the finished pole
Cutting, press forming, welding, inspection and loading under one roof and one certified quality system.
- Processes
- cutting, press forming, rolling, welding, inspection and loading in one plant
- Cranes
- overhead cranes, including 3 × 5 t
- Galvanizing
- hot-dip galvanizing at approved partner plants
- Quality system
- factory production control certified to EN 1090-1 · welding quality to EN ISO 3834-2
- Location
- Kočani, eastern North Macedonia · road transport across Europe

- 01
CNC cutting
Plate blanks, base plates and flanges cut on CNC plasma.
- 02
Press forming
Half-shells formed on the 12 m tandem press brake.
- 03
Seam welding
Automatic submerged-arc welding of the longitudinal seams.
- 04
Inspection
Fit-up, visual and dimensional checks before release.
- 05
Finish & dispatch
Hot-dip galvanizing to EN ISO 1461 · loading from our own yard.
Film
See our production
Conical poles, octagonal poles and high mast sections on their way through our halls in Kočani — cutting, forming, welding and loading.
The video is played by YouTube. When you press play, your browser connects to YouTube (Google), which receives your IP address and may store data on your device. Privacy policy
Forming capacity
12-metre tandem press brake
Two synchronised press-brake units operate as one machine with a 12 m bending length. Tapered half-shells are formed along their full length — the basis for polygonal pole and mast sections of up to approx. 12 m with two longitudinal seams.

Schematic, not to scale.
Machine data
- Type
- CNC tandem press brake · two units
- Synchronisation
- Electro-hydraulic · four cylinders
- Bending length
- 2 × 6,000 mm (12,000 mm)
- Throat depth
- 1,500 mm
- Ram stroke
- 400 mm
- Open height
- 1,500 mm
- CNC control
- Delem DA66T
Machine data from the manufacturer’s documentation.
Two half-shells, two seams
Every polygonal section is made from two longitudinal, tapered half-shells. Each half is bent along its full length on the tandem press brake; the two halves are then joined by two longitudinal seam welds.
- 01
CNC-cut blank
Tapered plate, plasma cut to the developed shape.
- 02
Press-braked half-shell
Each half formed on the 12 m tandem press brake.
- 03
Two halves, two seams
Closed by automatic submerged-arc (SAW) welding.
- 04
Slip-jointed sections
Sections up to approx. 12 m; taller masts by slip joints.


Cutting & rolling
CNC plasma cutting and plate rolling




CNC cutting
- Cutting
- CNC plasma cutting · Hypertherm MAXPRO200
- Parts
- Developed shaft blanks, base plates, flanges, gussets and door reinforcements — cut to the nested shape
Plate rolling
- Rolling
- Three plate-rolling machines
- Working width
- 3,100 mm
- Parts
- Cylindrical and conical shells
Welding
Automatic seam welding
Long shaft and mast seams are welded by automatic submerged-arc units. Base plates, door frames, brackets and stiffeners are welded by MIG/MAG.
- Equipment
- Column-and-boom and carriage submerged-arc units · CNC longitudinal seam welding line · MIG/MAG stations
- Coordination
- Welding coordination by IWE-qualified welding engineers
- Welders
- Qualified to EN ISO 9606-1 · welding operators to EN ISO 14732
- Procedures
- Qualified welding procedures for submerged-arc (121) and MAG (135) welding of S235 and S355 steels

- Open photograph: Column-and-boom submerged-arc welding of a mast section · November 2025

- Open photograph: Longitudinal seam welding

- Open photograph: Submerged-arc seam — longitudinal seam of a polygonal section

- Open photograph: MAG welding — manual welding of details (process 135)

- Open photograph: Welding control — automatic welding parameters at the unit

- Open photograph: Attachments — stiffeners, lugs and fittings

- Open photograph: MAG welding of a plate assembly · Kočani plant


Galvanizing steps: degreasing · pickling · fluxing · dipping in molten zinc · cooling and inspection.
Surface protection
Hot-dip galvanized
Where specified in the order, poles, masts and accessories are hot-dip galvanized to EN ISO 1461 at approved partner plants — inside and outside, in one dip where the section length allows.
- Standard
- EN ISO 1461 — coating thickness according to the steel thickness
- Fasteners
- Threaded parts galvanized to EN ISO 10684
- Design
- Vent and drain openings in every section · section lengths agreed with the galvanizing plant
- Appearance
- Variations in colour and gloss are normal for hot-dip galvanized surfaces
- Records
- Galvanizing certificate for galvanized deliveries, as agreed in the order
- Other systems
- Further coating systems to the client’s specification, on request
- Surface preparation
- Shot blasting before coating, where specified
Production equipment
Machines in our halls
- Forming
- Tandem CNC press brake 12 m (Delem DA66T) · press brake 6 m
- Cutting
- CNC plasma cutting · Hypertherm MAXPRO200
- Rolling
- Three plate-rolling machines, 3,100 mm working width
- Welding
- Automatic submerged-arc welding (column-and-boom and carriage units) · CNC longitudinal seam welding line · MIG/MAG stations
- Other
- Shot blasting · heavy section bending press
- Long sections
- Work stations are laid out for shafts and mast sections of up to approx. 12 m in one piece.
- Own cranes
- Overhead cranes, including 3 × 5 t, for safe handling from cutting to loading.
- One quality system
- All production steps run under one certified factory production control.
Logistics
Packed, loaded, delivered
Complete poles and sections of up to approx. 12 m are bundled, protected and loaded with our own cranes — for road transport across Europe.

- Packing
- Bundles with timber spacers and straps · protection of threads and flanges
- Loading
- Overhead cranes in the hall · side- and rear-loaded trailers
- Transport
- Road transport across Europe on standard trailers
- Terms
- Ex works / FCA Kočani or delivered to site (DAP) — per offer, Incoterms 2020
- Marking
- Each section and bundle marked to the delivery list
- Documents
- Packing list and CMR · material and galvanizing certificates as agreed in the order
Enquiry
Request a technical manufacturing review
Send drawings, loads and specifications — we review manufacturability before we quote.